|
What should I be concerned with when developing my data
center?
There are lots of different areas you
need to focus on. I will divide my answer into data
center facility related areas of focus and IT areas of
focus. As you might expect, the two tend to drive each
other in a circular fashion.
Start with the IT side – you will need
to clearly define the current state of the environment
and how it might change when you migrate to the new
location. The migration itself sometimes drives the
changes out of necessity. You need to know both the size
of the current environment and have projections of where
it will go within a reasonable horizon of the new data
center’s life. Where will the number of servers be in
three years and five years? The one thing you can be
sure of is that whatever growth number you choose will
be wrong, but you will at least have some level of
projections. You will also need to understand the extent
you will virtualize the new environment, as well as how
data will grow and what impact that will have on storage
arrays, SANs, etc. The bottom line in this early mode is
to use the IT numbers to project space and power
requirements. Power will drive heat and hence air
conditioning requirements.
When you get to the facility side, you
will need to focus on such issues as redundancy and
diversity. I am sure you can find the best practices in
these areas. If not let me know and I can send you some
good info. From the electrical perspective, focus on
delivering the amount of redundancy that your business
needs. Most data centers today use two redundant paths
to deliver electricity to the equipment. Remember that
this “dual path” needs to go from the PDU in the cabinet
all the way to the utility feed from the street. One
area to focus on here is to understand how much
additional switching you would like to add to the
design. In other words, if you lose one feed from the
street (one of your paths in) do you want to switch the
UPS that utility connection feeds to the other feed from
the street to maintain redundancy upstream? Same can be
said on the other side of the UPS. This redundancy
discussion takes you into the discussion of service
level agreements to your customers (and from your
provider if outsourced). It also drives the decision of
architectural Tier level. Also on the electrical side,
pay specific attention to providing the ability to
measure power consumption at all levels, from UPS and
panels through cabinet level PDUs.
Electrical Redundancy is actually
pretty simple compared to the Air Conditioning
environment. There are many options in this area
including air and water cooled systems, in line cooling
systems, aisle containment, raised floor or overhead
delivery, etc. This is a relatively complex discussion
and more than I can do a good job describing here. Let
me know if you would like to discuss this offline. My
best advice here is to get a great Mechanical/Electrical
Engineering firm (I can give you some references) that
has experience in advanced designs – to leverage the
most efficient architectures available today. Never,
ever (ever, ever, ever) choose an engineering firm that
sells equipment! You will absolutely get a combination
of whatever they sell – never what is the best for the
application. Also, focus on the HVAC control system,
understanding sequencing of the air conditioners, both
how they fail over and how they fail back. From a
measurement standpoint, be sure to provide the ability
to measure temperature and humidity levels within the
equipment area. I usually like to be able to get at
least one point of measurement per cabinet position and
many organizations measure many more points. Do not
skimp here.
For both the electrical and mechanical
systems, make certain that the design takes into
consideration what happens when there is scheduled (or
unscheduled) shutdowns of the supplies. In a multitenant
building electrical and condensed water risers are
occasionally shut down for maintenance, to add tenant
taps, etc. What happens if both your primary and
redundant air conditioning systems rely on the same
condensed water riser? Make sure there is a back-up plan
here.
When construction is started, ask to
have the Communications Carrier (Telco) room made
available first. I usually can get this room turned over
to IT weeks to a month or two before the rest of the
data center and this can work wonders in completing the
carrier installs in parallel with the data center
build-out.
When the data center is ready be sure
to schedule a formal commissioning test of each of the
major critical systems (UPS, Air Conditioning,
Electrical switches, generators, etc.) The commissioning
of the Air Conditioning should include the control
automation and all of the failure modes should be
tested.
While all of the design and
construction work is going on, the IT organization needs
to be working hard on developing the plan on how all of
the systems will migrate over. Some of the key areas to
focus on here is the methodology of the migration. This
can include new instances of an application in the new
data center, which can be either physical or virtual
instances, or the relocation of the physical equipment
to the new environment.
When migrating applications two
standard areas to focus on are IP sensitivities and data
migration. Your equipment will clearly be moving to a
new IP subnet, which may have the effect of breaking the
application. Best to test for this before migration.
Data migration can be a huge undertaking. People often
immediately jump to the solution of moving the data over
the wire, however when the datasets get very large this
becomes problematic in a functioning environment. The
window to move the data may be smaller than the time it
would actually take for a large dataset.
My experience on Data Center builds is
that Facilities owns the construction and IT drives the
requirements. Make certain that there is a very close
collaboration between the groups for this to work at
all. Most of all get a super PM that has done this many
times. This is absolutely no place to learn the
business.
Finally, one of the other members of
the data center group also suggested you put some
detailed initial focus into the legal aspects of the
relationship. If outsourced this means SLAs, if company
owned make certain all of the required rights are in the
lease and in both cases the appropriate remedies if you
do not get what you contracted for.
These are a few of the big
issues that come to mind. Most all of these issues are
equally important of you are building or going to an
outsourced location.
|